Adobe certification Adobe
Apple certification Apple
Avaya certification Avaya
Business Objects certification Business Objects
Check Point certification Check Point
Cisco certification Cisco
Citrix certification Citrix
CIW certification CIW
Cognos certification Cognos
CompTIA certification CompTIA
CWNP certification CWNP
ECCouncil certification EC-Council
EMC certification EMC
Exam Express certification Exam Express
Exin certification Exin
F5 Networks certification F5 Networks
FileMaker certification FileMaker
Hitachi certification Hitachi
HP certification HP
Hyperion certification Hyperion
IBM certification IBM
Isaca certification Isaca
ISC certification ISC
ISEB certification ISEB
Juniper certification Juniper
Lotus certification Lotus
LPI certification LPI
McData certification McData
Microsoft certification Microsoft
Mile2 certification Mile2
MySQL certification MySQL
Network Appliance certification Network Appliance
Network General certification Network General
Nortel certification Nortel
Novell certification Novell
OMG certification OMG
Oracle certification Oracle
PMI certification PMI
SAIR certification SAIR
SAS Institute certification SAS Institute
SNIA certification SNIA
Sun certification Sun
Sybase certification Sybase
Symantec certification Symantec
Teradata certification Teradata
Tibco certification Tibco
VMware certification VMware
All Exams

Microsoft 70-301 Exam - BestSheet.com

Free 70-301 Sample Questions:

1. Look at the picture.
Drag and drop question. Drag the items to the proper locations.

Answer:


2. You are responsible for the Program Management role on a project. The project is currently in the Planning Phase. The project goal is to develop a Web application. Scalability was rated as the most important architecture design goal. You need to identify the scalability design goal at the logical level. Which design goal should you identify?
A: Use Microsoft Windows NT Load Balancing Service (WLBS).
B: Ensure that the application can support 5,000 users.
C: Use a load-balancing solution.
D: Implement the load-balancing solution by using an in-house team.
Answer: C

3. You are responsible for the Program Management role on a project. The project is currently in the Developing Phase. The team identifies and analyzes a number of risks. To prioritize risks, the team decides to use a numeric probability scale between 0 and 1, and a numeric impact scale from 1 (low) to 10 (high). The analysis of the risks that were created in the Envisioning Phase is shown in the exhibit. (Click the Exhibit button.) You review the master risk list. The project budget for the required hardware was approved after the Envisioning Phase. The customer might be reassigned to another job outside the country, but the impact of this risk was reduced from 9 to 7. The customer designated a replacement, and that person is in training. All other risk probability numbers and risk impact numbers remain the same. You need to reassess the master risk list by using this new information. Which risk is the top priority risk?

A: If the currently proposed legislation does not pass into law, the project will be canceled.
B: If the customer is reassigned to a job outside the country, the project will lose its sponsorship.
C: If the project budget for the required hardware is not approved, the scalability and throughput requirements will not be met.
D: If the team is asked to complete tasks that are not in the current project, the project schedule will slip by two weeks.
Answer: B

4. You are in the Development role on a project for your company. The goal of the project is to implement a data warehouse solution. The project is currently in the Planning Phase. The functional specification is submitted to the chief data architect for approval. She returns it for revision and includes the following comments: The proposed functionality conforms to the scope. The usage scenarios that are described are realistic and accurate. The design for the data warehouse and analysis tools seems technically feasible. The amount of disk space that is allocated for data storage in the design might be inadequate to manage future growth. You need to produce a solution specification that meets the chief data architects needs. What should you do?
A: Produce a revised conceptual design.
B: Produce a revised logical design.
C: Produce a revised physical design.
D: Produce a detailed development plan.
Answer: C

5. You are responsible for the Program Management role on a project. The project is currently in the Planning Phase. The project trade-offs are shown in the following table. Fixed Chosen Adjustable Resources X Schedule X Features X A logical design was approved by the companys IT management team. You are preparing the physical design. You realize that the hardware requirements to implement the logical design will exceed the available budget.This problem might cause the project to be canceled. You need to ensure that the project can proceed. What should you do?

A: Negotiate additional budget with IT management.
B: Postpone the project until the next financial year.
C: Perform a pilot deployment by using the available hardware.
D: Revise the logical design so that it has lower hardware requirements.
E: Perform a pre-production test deployment by using the available hardware.
Answer: D

6. You are responsible for the Program Management role on a project. The project team identifies the following risk conditions: The solution requires new hardware drivers that might be late. The developers might not have experience in using the software that is selected. There might not be enough testers available. The Release Management role might leave the team. You need to identify the risk consequences that are most likely to occur as a result of these risk conditions. Which three risk consequences should you identify? (Choose three.)
A: Development might take longer than planned.
B: Versioned releases might not be possible.
C: Risks might occur, but contingency plans might not be invoked.
D: The deployment might be late.
E: The help desk might not be able to resolve user support requests.
F: A proof of concept might not be performed.
Answer: A, D, E

7.You are responsible for the Program Management role on a project. The goal of the project is to implement a new e-mail solution. The logical design is currently in development. The Development team notifies you that its members do not understand all the different ways in which users will access their e-mail messages. The team members need more information before they can proceed. You need to ensure that the team can finish the logical design. What should you instruct the team to do?
A: Modify the scope document to more clearly state requirements.
B: Define usage scenarios.
C: Develop the physical design.
D: Perform a series of usability tests.
E: Define and document user profiles.
Answer: B

8. You are responsible for the Program Management role on a project that recently started the Planning Phase. The solution will be created in two versioned releases. The project team made this decision to allow feedback from version 1 to influence the requirements for version 2. The Release Management role informs you that because of operational constraints, your team will only be permitted a single release to production. You need to evaluate how this change will affect the project. Which two issues or risks does this change introduce to the project? (Choose two.)
A: More time will be needed for requirements analysis.
B: Less time will be available for testing.
C: The release process will need to be automated.
D: The solution will come to market later.
Answer: A, D